Regeneration

Council's Regeneration Proposal

News Upload Date: 29th January, 2024








Lancaster Area Regeneration Proposal

Belfast City Council Regeneration Team have a design team appointed who are looking to bring Lancaster Street proposals forward in conjunction with the works to LYS-LPS i.e. as one tender package and one contractor.  They would like to present regeneration proposal drawings to local stakeholders and local residents.

See below for the proposal document information provided by the Belfast City Council Regeneration Team.

Proposal Objectives

Objectives – Declutter and Personalise

Zone 1 – Pedestrian entrance to Lancaster Street from York Street, c100m2.

Zone 2 – Segregated space to Lancaster Street Car Park, c 85m2.

Zone 3 – High Level Security fencing, c40m.

Regeneration Zones

Ariel View Lancaster Area/ York Street.

Regeneration Zones

Ariel View Lancaster Area/ York Street.

Zone 1 - Pedestrian entrance to Lancaster Street from York Street.

Zone 1 – Pedestrian entrance to Lancaster Street from York Street, c100m2. Create gateway entrance point to Lancaster Street, by:

Replacing existing brick paving with natural stone paving (as per Little Patrick/Little York Street Proposals).

Removal of brick planter.

Relocation of BT Pole.

Removal/amendments to low level curved wall (pending landowner agreement) to remove potential dwell space.

Removal of low level demarcation brick wall and demarcate land ownerships boundary via pavement detail.

Level adjustment/localised retaining solution to provide uniform levels.

Re-set of existing utility covers.

Mural opportunity for (grey) gable wall (pending community consultation).

Mural opportunity for brick wall (pending community consultation).

Traffic restriction solutions via bollards/art work (pending community consultation).

Zone 2 - Segregated space to Lancaster Street Car Park.

Zone 2 – Segregated space to Lancaster Street Car Park, c 85m2. Removing segregation and maximise future public realm space by:

Removal of heras fencing demarcating public footpath (presumed DfI Roads ownership) and Belfast City Council owned land within carpark.

Re-establish demarcation in pavement make up (e.g., pin kerb).

Re-surface hard standing in asphalt / traditional pavement make-up (future proofing for the instance of future strategic road improvements).

Replace existing bollards with new bollards / art work (pending community consultation).

Mural opportunity for brick wall (pending community consultation).

Zone 3 - High Level Security fencing.

Zone 3 – High Level Security fencing, c40m. Removing segregation and maximise future public realm space by:

Replace security fencing to top of brick wallin consultation with landowners / residents. Materiality TBC.

The proposal information shown has been provided by the Belfast City Council Regeneration Team.